Segment 1, 2 and 3 Construction
Construction activities are underway on Segment 1 in Morgan and Weld counties. Construction activities continue on Segments 2 and 3, including at Canal Crossing, Goose Creek and May Valley substation. Additional construction activities will be initiated as construction permit approvals are granted by each jurisdiction.
Construction activities include the use of helicopters to aid in the stringing of wire between poles. Xcel Energy will coordinate with the Federal Aviation Administration and local officials during operations.
Learn more about the Transmission Line Construction Process.
Interactive Construction Map
Zoom in and click on the interactive map below to see details on current construction activities along Segments 1, 2 and 3 of Colorado’s Power Pathway. This map reflects the latest construction activities:
Interactive Construction Map Keys | ||||
Color | Transmission Line Construction Phase | Color | Substation Construction Phase | |
Grey | No Current Construction | Grey | No Current Construction | |
Yellow | Site Preparation | Yellow | Site Preparation | |
Green | Install Foundation or Vibratory Caisson | Blue | Grading | |
Orange | Set Transmission Pole | Green | Install Equipment Foundations | |
Purple | String Conductor Wire | Orange | Install Equipment | |
Black | Restoration | Black | Restoration |
Solid dark and light red lines represent township and section boundaries.
Additional revisions may be posted; please check back as this map will reflect the most up-to-date information.